PM Surya Ghar last date is 31 March 2027: what UP applicants should finish, and by when
By BL Solar Solutions · Reviewed by Aditya KumarPublished · 8 sources
In this article (7 sections)
The PM Surya Ghar last date is 31 March 2027. MNRE's scheme guidelines say "the implementation period of the scheme shall be till 31st March, 2027", and the national portal shows a countdown under the line "Scheme closes on 31 March 2027". No official document says what happens to an application that is still in progress on that date, and no extension has been notified. When the earlier rooftop scheme (Phase II) ended, applications that were not installed by the cut-off were declared ineligible for the subsidy and deleted from the portal. So the safe plan is to have every step done, including redeeming your subsidy, well before 31 March 2027. If every later step takes its full official time, a UP home whose vendor agreement is uploaded after late December 2026 may not finish in time.

This guide is built from MNRE's PM Surya Ghar guidelines and portal notices, and UPNEDA and Uttar Pradesh government documents. It does not draw on BL Solar's own records.
What the official documents say
| Source | What it says |
|---|---|
| MNRE scheme guidelines, section 2(d) | "The implementation period of the scheme shall be till 31st March, 2027." Section 1(a) says the scheme is to be implemented till FY 2026-27. |
| National portal home page | "Scheme closes on 31 March 2027", with a countdown. On 23 November 2026 it showed 128 days left. |
| MNRE notice to vendors, 24 August 2026 | Opens with "less than 9 months remaining before the conclusion of the PM Surya Ghar (PMSG) scheme". It deactivated 66 vendors that held far more agreements than they could install, and told vendors not to keep applications for more than 60 days without a valid reason. |
| Portal announcement on Phase II | "Phase-II Applications submitted but not installed as on 01.04.2025 are ineligible for CFA and have been deleted from database." CFA is the central subsidy. |
| MNRE scheme guidelines, section 8(c) | The scheme accepts up to 1 crore active applications. Once that limit is reached, MNRE may set a time period for completing installations. |
The portal showed 92,83,824 applications and 58,19,430 installations as on 22 November 2026. That total includes applications that are no longer active, and the portal does not say how many are active, so it does not tell you how close the 1 crore limit is.
What is not decided yet
- Applications in progress on 31 March 2027. No PM Surya Ghar document says whether they will still be installed or paid. The Phase II example above is the only official precedent, and it was strict.
- An extension or a second phase. News reports since August 2026 have said MNRE may extend the scheme by a few months or plan a successor scheme. On 23 November 2026, the What's New list on the national portal had no notice of either. Plan for 31 March 2027 until an official notice says otherwise.
Work backwards from the PM Surya Ghar last date
The table counts back from 31 March 2027 using each step's official time limit. It shows the latest date each step can finish if every step after it takes its full allowed time. This is arithmetic on the limits, not a promise. Real steps are often faster, and sometimes slower.
| Step | Official time limit | Latest date, counting back |
|---|---|---|
| UP state subsidy paid by UPNEDA | 7 days after the central subsidy (UPNEDA booklet) | 31 March 2027 |
| Central subsidy paid | 15 days after DISCOM approval (MNRE guidelines, 6(t)) | 24 March 2027 |
| DISCOM approves the installation, and you redeem the subsidy | Commissioning within 15 days (Electricity (Rights of Consumers) Rules, as amended in 2024) | 9 March 2027 |
| Vendor finishes the installation and submits the details | 22 February 2027 | |
| Vendor agreement uploaded on the portal | You can change vendor if installation details are not submitted within 60 days (portal announcement) | 24 December 2026 |
| Vendor agreement uploaded, if the vendor uses the full time the UP policy allows | 90 days for installation (UP Solar Energy Policy 2022, 7.2(j)) | 24 November 2026 |

Representative image
What to do now, by stage
You have not applied yet. Apply on the national portal now and choose a registered vendor with a record of completing installations. Our guide to checking a solar vendor before you pay lists the official checks. Ask the vendor, in writing, for an installation date before you approve the agreement.
You have chosen a vendor, but the agreement is not uploaded. Ask the vendor to upload it this month. Since September 2026 the agreement waits for your approval in your own login, so check your login and SMS after the vendor uploads it, and approve it the same day if the cost is right.
The agreement is uploaded, but nothing is installed. Ask for a written installation date. If installation details are not submitted within 60 days of the agreement upload, the portal lets you switch to another vendor (for applications without a loan). Note that the portal now asks for your bank details before the installation details are submitted.
The system is installed, but not commissioned. The DISCOM should commission it within 15 days. If it does not, contact the DISCOM's nodal officer for PM Surya Ghar or raise a grievance on the portal. Our guide to PM Surya Ghar application status in UP explains every stage and who acts on it.
The system is commissioned. Add your bank details and click "Redeem Subsidy" in your login straight away. Nothing is paid until you do. Our guide to how many days the solar subsidy takes explains the redeem steps and the validation checklist.
Fix your name now, not in March
The portal's announcements say the applicant's name in the bank must exactly match the name on the DISCOM electricity bill, "otherwise, the application for subsidy release shall not be processed". Since 3 September 2026, applications with a "confidence score below 70%" are not redeemed directly. The consumer must download an undertaking, sign it and upload it with a government name proof such as Aadhaar or a voter ID. The announcement does not say which score it means; the bank details screen in your login shows a name-matching score.
A name change with the DISCOM or the bank can take time. Compare the names on your bill and your passbook today, and start any correction now.

Representative image
The UP state subsidy has its own policy period
The UP state subsidy of Rs 15,000 per kW, up to Rs 30,000, comes from the Uttar Pradesh Solar Energy Policy 2022. The policy says it remains in operation "for a period of five (5) years or till the Government notifies the new policy whichever is earlier", and its incentives are available "during the Operative Period of the policy". The policy was issued in 2022, so its five years also end in 2027. UPNEDA releases the state subsidy only after the central subsidy is paid, so finishing the central steps early protects both.
Not sure how much time your application needs?
Send a screenshot of your application tracker on WhatsApp to +91 92609 40733, with your name and consumer number hidden. We will tell you which step it is on and what has to happen before 31 March 2027.
Related guides:
Sources
- Ministry of New and Renewable Energy, Operational Guidelines for PM Surya Ghar: Muft Bijli Yojana, CFA to Residential Consumers (7 June 2024, amended to 31 August 2026): sections 1(a), 2(d), 4, 6(t) and 8(c), under What's Newpmsuryaghar.gov.in · Accessed 23 November 2026
- PM Surya Ghar National Portal, home page ("Scheme closes on 31 March 2027", figures as on 22 November 2026) and announcements (Phase II, vendor change, bank details, name match, confidence score)pmsuryaghar.gov.in · Accessed 23 November 2026
- MNRE, "Notice to Registered Vendors: Time-Bound Performance Mandate for Clearing Pending Applications", 24 August 2026, under What's Newpmsuryaghar.gov.in · Accessed 23 November 2026
- PM Surya Ghar National Portal, notice "Consumer Verification of Agreement Upload", 23 September 2026, under What's Newpmsuryaghar.gov.in · Accessed 23 November 2026
- Press Information Bureau, "Electricity (Rights of Consumers) Amendment Rules, 2024", 23 February 2024pib.gov.in · Accessed 23 November 2026
- Government of Uttar Pradesh, Uttar Pradesh Solar Energy Policy 2022, sections 3.2, 7.2(j) and 7.3(a) (hosted by UPNEDA)upneda.org.in · Accessed 23 November 2026
- UPNEDA, "PM Surya Ghar: Muft Bijli Yojana Information Booklet", Stage 5 (subsidy disbursal timelines)upneda.org.in · Accessed 23 November 2026
- UPNEDA, DISCOM-wise nodal officers for PM Surya Gharupneda.org.in · Accessed 23 November 2026
Related guides

BL Solar Solutions
Editorial Team
Published by BL Solar Solutions, a UPNEDA registered rooftop solar installer with 10+ years of experience in Uttar Pradesh.